1890’s
Winscombe School Opens
1979
The Winscombe Community Association is formed
2013-14
Sub-committee formed to examine future development plans
Initial consultations with community and local facility owners held to establish community needs. The Project to be called Winscombe New Space or WiNSpace for short
Oct 2014
WiNSpace project committee expanded to include other non-trustee members of the community. Widespread consultation with the organisations including local groups, hall and clubs.
2015
Talks began between the WiNSpace project and St James’s on possible WCA/Church joint project
2016
Section 106 Application made to North Somerset and Parish Council for £300,000 to support the WiNSpace project to update their current buildings. This was included as part of the Woodborough Farm Redrow planning recommendations As part of the planning approval in Dec 2016 an award of £300,000 was granted as a contribution towards enlarging / refurbishing / rebuilding the Winscombe Community Centre.
2016-18
First Ideas
Stride Treglown selected as our architects drawing on their experience with the Congresbury community centre project. They created our initial designs and put together a pre planning application
2018
Following a survey of the congregation the Church decided not to proceed with the current joint venture idea
Aug 2019
With the feedback received from North Somerset Planners, an estimated cost for the ‘big build’ design and the Church no longer involved with the project, four options where put to the Parish – Option B was adopted.
Nov 2019
Winscombe Community Association becomes a Charitable Incorporated Organisation (CIO)
2019-22
New Community Building design created by B2 Architects and full planning approval received from North Somerset Council in February 2022 after a 11 month planning process
2021
1st Lottery bid for £500,000 unsuccessful creating a hole in our funding plan, although a smaller bid to the fund in the future would be possible.
June 2021
Parish Council agree to support the project after a survey which showed the idea of a new community space in Winscombe had over 80% support. This was in two forms a Grant for £250,000 and a Loan to the WCA of £250,000.
May 2022
Following the Covid epidemic and Ukraine conflict, building materials and labour costs soar, increasing likely cost of WiNSpace from £2.2M to £3.5M. This required a further rethink of the building design.
Dec 2022
New funding source identified from the Government which allowed an application of £300,000 to be made
Feb 2023
Latest building design agreed
By using the upstairs space in the south wing, which was initial there for future expansion (replacing the north wing large hall). A new building design was created which gave spaces with a similar floor area but at a much reduced cost.
June 2023
Trustee agree to go for latest design with good viability of likely funds.
Work commences to update the business plans and to start the process of applying for grants from multiple organisations. The challenge was to start the build during 2024. The agreed approach was to use a phase building strategy. Phase 1 was to construct the new building to replace the old out buildings. Phase 2 was to refurbish the old school to re-purpose to be focused on the youth. Phase 3 would be the construction of the large auditorium when the was a need and funding for it
Oct 2023
Professional Design Team put together to create a full specification and tender document for the new building design.
Dec 2023
With the possibility of building to start in 2024 the Go WiNSpace 24 campaign was launched by the Trustees
Feb 2024
Funding for New Building identified and awarded
After applying for many grants the WiNSpace team have been awarded nearly £1,000,000 of grants which combined with their and other local funds a total of £1,700,000 was reached. This was enough to confidently give the go ahead to sign a contract for the new building
Aug 2024
Construction Company Appointed and final planning received
Following a robust tender process which started in March 24 Rigg Construction Ltd were appointed to construct the phase 1 building. At the same time WiNSpace received North Somerset Planning approval for their phase building approach.
Sept 2024
Transition starts
With the imminent demolition of the youth club, Art Shed and sale of the headmasters house the spaces were cleared in readiness
Oct 2024
Headmasters House sold to help fund the new community building
Dec 2024
Demolition of Youth Club and Art Shed starts with the removal of the Asbestos
Jan 2025